Case Study: ArcelorMittal AZ Sheet Piles Temporary Strong Points for Off Shore Wind Turbines

ArcelorMittal AZ Sheet Piles Temporary Strong Points for Off Shore Wind Turbines

Contract No:C827
Client:DONG Energy
Location:Walney Island, Barrow-in-Furness
Value:Approximately £503,000.00
Summary:Installation of ArcelorMittal AZ Sheet Piles to form 2no 'Strong Points' to support a 1300Te Crawler Crane to load tubular mono-piles for off shore wind turbines.

Sheet Piling (UK) Ltd were employed by DONG Energy to carry out the installation of ‘Free Issue’ ArcelorMittal AZ sheet piles to form 2no ‘Strong Points’. The ‘Strong Points’ were required to provide suitable access points for 2no 1300Te Crawler Cranes which were required for lifting up to 800Te tubular mono-piles.

The works were completed to form wind turbine foundations for the Walney Off Shore Wind Farm Phase 2. In total 42no pairs of AZ25 ArcelorMittal Sheet Piles and 20no pairs of AZ14 Arcelor Sheet Piles, in Grade S355GP Steel, were installed to each ‘Strong Point’ which were each approximately 21m & 19m on plan.

Prior to installing the steel sheet piles, approximately 6000Te of quarried aggregate stone was back-tipped for the existing dock to provide a suitable sheet piling platform. Once installed, the ArcelorMittal sheet piles were tied together using an ArcelorMittal tie rod and waling beam system.

Each ‘Strong Point’ was then completed by topping up with stone to tie in with existing quay levels together with bollard installation. Upon completion of the Walney Off Shore Wind Farm, the Arcelor Sheet Piles are anticipated to be extracted to reinstate the quay to its original condition.